Nansha No. 2 Middle School Project
Basic information about the project
Nansha No. 2 Middle School covers an area of 112,900 sq yards with a building area of 48,420 square yards.
What aspects of work are we responsible for
VMKON remodeled all sports venues, such as the swimming pool, table tennis hall, basketball court, and badminton court for Nansha No. 2 Middle School.
Problems encountered in the process.
The problem of uneven ground is because the drawings require the removal of the original EPDM floor and then laying the suspended floor directly; our company found that the original cement floor was uneven after removal, resulting in water accumulation on the ground, after communicating with the school, our company adopted the method of ground slotting Run the water into the drain. solved the problem very well
School Evaluation
Dealing with problems flexibly and efficiently. The product quality is very good. The design service is in place. The venue has a new look.